Video documentation of the installation of the double floor of the WEDOS data centre under construction in Hluboká nad Vltavou – from the unloading of the truck to the final state.
Continue reading “VIDEO: Laying a double floor”IMAGE: Laying a double floor
These days the installation of the double floor is in progress. First we started by taking the material off the truck. Follow the progress of the work day by day with us.
Continue reading “IMAGE: Laying a double floor”IMAGE: Hardware testing
Testing of hardware loaned to us by potential suppliers is underway. It is not about testing as much as it is about familiarization, exploring options, tool management, etc.
Continue reading “IMAGE: Hardware testing”VIDEO: Rough construction
A few shots of the interior and the ongoing construction work.
Continue reading “VIDEO: Rough construction”IMAGE: Concrete Day
Saturday 24.7.2010 was marked by the concreting of the floor. It rained continuously all day, but we were sheltered in the premises of the emerging datacenter.
Continue reading “IMAGE: Concrete Day”IMAGE: Rough construction
(update 5.8.) Photogallery showing rough construction work – demolition of original premises, cutting concrete walls, masonry and painting work, cleaning
Continue reading “IMAGE: Rough construction”