These days the installation of the double floor is in progress. First we started by taking the material off the truck. Follow the progress of the work day by day with us.
Continue reading “IMAGE: Laying a double floor”Crystal Lupa Competition – support us
The annual Crystal Lupa – a competition for the most interesting and popular projects and services on the Czech Internet – has started. If you like our data centre project as a reality show, support us in nominations and voting, you will be entered into a prize draw.
Continue reading “Crystal Lupa Competition – support us”Career: hardware and network administrator
We are looking for an experienced hardware administrator to join our team – servers, network elements, storage and more. Job description includes hardware selection and purchase, testing, installation, repair, infrastructure development.
Continue reading “Career: hardware and network administrator”Career: Linux Server Administrator
We are looking for an experienced Linux OS server administrator to join our team to run hosting services, database systems, virtualized solutions, web applications, storage and more.
Continue reading “Career: Linux Server Administrator”IMAGE: Hardware testing
Testing of hardware loaned to us by potential suppliers is underway. It is not about testing as much as it is about familiarization, exploring options, tool management, etc.
Continue reading “IMAGE: Hardware testing”Project status and plan for August
The construction of the data centre is in full swing, with rough construction finishing. We have many other things coming up in August – double flooring, electrical work, installing SHZ, UPS and air conditioning and more.
Continue reading “Project status and plan for August”VIDEO: Rough construction
A few shots of the interior and the ongoing construction work.
Continue reading “VIDEO: Rough construction”VIDEO: Rough construction
A few shots of the interior and the ongoing construction work.
Continue reading “VIDEO: Rough construction”IMAGE: Concrete Day
Saturday 24.7.2010 was marked by the concreting of the floor. It rained continuously all day, but we were sheltered in the premises of the emerging datacenter.
Continue reading “IMAGE: Concrete Day”Acoustic assessment
Due to the very complicated situation regarding the location of the air-conditioning units and the motor-generator in the built-up centre of the town, it was necessary to prepare a noise study (acoustic assessment), which shows what noise protection measures are needed.
Continue reading “Acoustic assessment”