In the last few days, the air conditioning units and one UPS unit have been gradually transported and moved into our building.
The air conditioning units were transported on Friday 20.8.2010 from Italy and were assembled in the area near our building, as the necessary moving facilities were not yet available. Their removal took place during Tuesday and Wednesday 24. a 25.8. It was a day-long operation. These were 6 indoor air conditioning units, each 800 kg, and 12 outdoor units.
For indoor units, the steel frames on which they will be mounted must first be made (they will not be placed on a double floor). The external units will be placed on the roof, but for the time being we have hidden inside, as again the steel structure for the roof must first be fabricated and complicated. The entire cooling system is then connected and commissioned.
Subsequently, a UPS (Socomec Delphys 120 kVA) from our partner company was also delivered. It will be waiting for the completion of the power distribution system and the connection to the entire system.